Welsh Water has submitted planning applications for a £600m programme to replace ageing water treatment infrastructure serving the Cwm Taf region in south Wales.
The scheme is the largest infrastructure project in the company’s history and will replace treatment assets that have served the area for more than a century.
New treatment works and pipelines
The main construction package will include a new water treatment works at Dan-y-Castell Farm near Merthyr Tydfil, treated water storage, a pumping station at Pontsticill and connecting pipelines.
A separate project will upgrade Llwyn-onn Water Treatment Works in Bannau Brycheiniog National Park, including additional water storage and pipeline connections.
Together, the projects are intended to allow the existing Pontsticill and Cantref treatment works to be retired as maintenance becomes increasingly difficult and costly.
Applications have been submitted to Merthyr Tydfil County Borough Council and Bannau Brycheiniog National Park Authority.
Procurement preparation
Welsh Water is sounding out contractors, investors and suppliers ahead of procurement starting in early 2027 under Ofwat’s Direct Procurement for Customers model.
The company is inviting the supply chain to an engagement event at ICC Wales in Newport on 10 November to discuss potential work with delivery partners and suppliers.
Earlier market engagement outlined a 25-year contract for a competitively appointed provider. A delivery partner appointment is targeted for August 2028, with regulatory completion planned for March 2032 followed by 12 months of testing.
The latest investment figure is £600m, compared with the £667m figure cited during the earlier market engagement process.
Updated plans
Welsh Water chief executive Roch Cheroux said: “As a company we need to deliver this critically important infrastructure for the benefit of our customers. The effects of climate change are already being realised in Wales, with extreme weather bringing more frequent storms and heatwaves, all increasing the pressure on our ageing water treatment assets.”
The revised proposals follow community consultation and include green roofs, habitat improvements and greater use of previously developed land at existing sites.