Staffordshire County Council says its Road Map to a Better Network has begun to improve the county’s roads one year after its launch, while warning that maintaining progress across more than 4,000 miles of network will remain a long-term task.
The plan focuses on longer-lasting repairs, faster defect detection, better coordination of works and securing additional funding for bridges and other structures.
Repair programme expanded
The council says it is increasing the use of whole-road and full-lane repairs to reduce repeat visits and future disruption. Improved condition surveys are also being used to identify problems earlier. Recent work included repairs to the A518 near Stafford after a fuel spill.
An additional £15m has been invested in road repairs and efficiency measures. Council teams repaired 5,000 potholes and other defects in September, the highest monthly total recorded by the authority.
The plan also involves using technology and local teams to identify and address defects more quickly, alongside closer coordination with utility companies and neighbouring authorities to limit disruption from roadworks.
Bridge funding campaign continues
Staffordshire is seeking long-term highways funding from central government, including £40.3m towards the £46.3m Chetwynd Bridge scheme.
The council said work has also progressed on major bridge projects, with Wodehouse Lane Bridge completed and the Wolseley Bridge scheme between Stafford and Rugeley advancing.
Peter Mason, Staffordshire County Council’s cabinet member for strategic highways, said the plan was intended to deliver visible improvements while changing how the authority managed its network.
“A year after we launched we can see it’s had an impact. However this is very much work in progress and we know we need to maintain this momentum,” he said.
“Ultimately this is all about keeping Staffordshire moving.”