Additional engineering work is being carried out on the West Midlands Metro extension between Wednesbury and Dudley after engineers identified a safety-critical issue during testing.
Transport for West Midlands (TfWM) said the issue had taken longer than expected to resolve and had affected the project timetable. Passenger services on the more than four-mile extension are still expected to begin in early 2027.
Testing and assurance nearing completion
The extension includes track, signalling, junctions and electrical systems. Testing has involved operating trams on the route while individual systems are examined, allowing issues to be identified and addressed before the infrastructure is approved for passenger use.
A TfWM spokesperson said: “During this process, a safety-critical issue was identified during testing and required additional engineering work before the extension could be approved for passenger service. Resolving this issue took longer than anticipated and has affected the project timetable.”
The testing and safety assurance programme, overseen by independent assessors, is now nearing completion. Driver training is expected to start shortly, covering route familiarisation, timetable testing and final operational preparations.
TfWM said the line would not open until it was satisfied that it was safe for passenger operations and all necessary approvals had been secured.
“Safety is, and always has been, our overriding priority,” the spokesperson said. “We will not compromise on safety to meet a particular date.”