Safety

Robot clears 25 tonnes of furnace slag at Northern Ireland power station

Leonard’s remotely operated Descender Duo removed slag from a 26m-high furnace at Lisahally Power Station, keeping six workers out of the confined space.

A remotely operated robotic arm has removed 25 tonnes of slag from a 26m-high furnace at Lisahally Power Station in Derry~Londonderry, Northern Ireland.

Industrial operations specialist Leonard developed the vertical-access machine after its existing Axis system could not be used because of the furnace’s geometry and surrounding pipework. The new robot, known as the Descender Duo, was designed, engineered and tested in seven weeks, according to Leonard managing director Mark Leonard.

Reduced shutdown time

Lisahally is a waste-to-energy facility operated and maintained by Burmeister & Wain Scandinavian Contractor (BWSC). It generates 15.8MW of electricity from grade C waste wood, which the operator says is enough to help power 40,000 homes and businesses.

Slag build-up on heating and reaction surfaces can reduce boiler efficiency, increase corrosion and create a risk of unplanned shutdowns. Previously, the boiler had to be powered down and cooled for between 24 and 36 hours before rope-access teams could enter the confined space and remove the material manually.

Leonard said the twin-arm robot was installed 24 hours after the boiler was shut down. The company reported that it removed the slag in 10 hours, compared with 36 hours for the equivalent manual operation, and kept six workers out of the vessel’s interior.

Plant manager Martin Doran said: “Once it was installed we were hugely impressed by its efficiency.” He added that the teams had needed to plan carefully to manoeuvre the machine into the furnace around site constraints.

Remote equipment

Leonard said the Descender is available in single-arm and twin-arm configurations, with 360-degree rotation. It joins the company’s Axis and Nano machines, which are used for refractory demolition and cleaning inside boilers, vessels and silos.

Martin Doran said that although the access crew was experienced, sending people into a warm, confined environment remained a safety concern that BWSC wanted to reduce.

Mark Leonard described the Lisahally operation as a first-of-its-kind demonstration of how remote equipment can maintain productivity while improving safety. He said the company was also considering adaptations for castable refractory demolition, refractory spraying, anchor cutting and welding across waste-to-energy, cement, metal and petrochemical facilities.