RAF Brize Norton reopens 3km runway after 16-week replacement

Aircraft have returned to RAF Brize Norton following the runway works, delivered as part of a wider £180m airfield infrastructure programme due to finish in late 2027.

Aircraft have resumed operations at RAF Brize Norton in Oxfordshire after the Defence Infrastructure Organisation (DIO), VolkerFitzpatrick and Aecom completed the replacement of the base’s 3km runway in 16 weeks.

The DIO handed the new runway back to air commodore Phil Reid, head of Air Infrastructure, on behalf of the RAF. The first aircraft landed on the runway on Friday 13 November.

Longer-life pavement

The runway has been built using Pavement Quality Concrete (PQC) and Grooved Marshall Asphalt (GMA). The DIO said the materials were selected to improve resilience to higher temperatures and the effects of climate change.

According to the organisation, the PQC is expected to more than double the runway’s service life compared with the materials previously used. The aim is to keep the base operational for decades while providing long-term value for money.

Aircraft were dispersed to several alternative locations during construction so that operations could continue while the runway was replaced.

DIO chief executive and director general infrastructure for the National Armaments Director Group Mike Green said: “This has been a tremendous team effort. Delivering at pace while maintaining our focus on the RAF’s operational needs is no small achievement. The collaboration between DIO, the RAF and our contractors has been outstanding, and the result speaks for itself.”

Wider airfield programme

The runway works are part of a wider £180m programme funded through the Defence Investment Plan. The programme also includes taxiway and associated infrastructure refurbishment, airfield lighting upgrades, and improvements to drainage and supporting infrastructure.

Those works are scheduled for completion in late 2027. VolkerFitzpatrick was appointed to deliver the runway replacement, with Aecom providing technical services throughout the project.

Reid said the work would strengthen the airfield’s long-term strategic and operational capabilities, safety and resilience. “This success has only been achieved with tremendous team effort, which will continue through to overall project completion late in 2027,” he said.

DIO principal project manager Bob Noyes added: “After an incredibly busy 16 weeks, it is fantastic to see aircraft returning home to RAF Brize Norton and using the new runway.”