Work to change the junction at Putney Bridge in Wandsworth will begin on 1 December, with construction scheduled to take place in stages until March, according to Wandsworth Council.
The scheme will move the pedestrian crossing on the west side of the bridge towards the centre of the junction. This will allow traffic turning left from Lower Richmond Road to receive about 42 seconds of green time, compared with 25 seconds under the current arrangement.
Overnight work planned
Initial work will involve changes to the kerb at the pedestrian island and the relocation of CCTV equipment. The council said the most disruptive activities would be carried out overnight to limit the effect on traffic.
The revised layout will also enable the removal of the small traffic island on Lower Richmond Road. Changes to traffic signals and other islands are intended to improve northbound movement through Putney High Street and the wider junction while retaining a safe pedestrian crossing.
Wandsworth Council estimates the project will cost about £450,000, including design fees and temporary traffic management. It said it had been pressing Transport for London to deliver the layout and signal changes as quickly as possible.
Part of wider congestion measures
Councillor Robert Morritt, leader of Wandsworth Council, said: “People here have been very clear with us about the impact of congestion in Putney, so we’re doing what we said we would do and taking practical action to improve the situation.”
He added: “These next works at Putney Bridge are about making sure traffic gets more green time and capacity is increased through the junction, making journeys more reliable.”
The junction project follows a series of smaller changes in the area, including additional lanes on Putney Bridge Road and Putney High Street, the removal of a traffic island outside Snappy Snaps and cycle lane wands on the approach to the junction, and the reinstatement of the original bus lane operating times on Putney Bridge Road.
The council has also introduced CCTV enforcement on Putney Embankment, widened the road near the TK Maxx bus stop and added lane markings outside Putney station.
In September, Wandsworth told its Transport Overview and Scrutiny Committee that congestion around Putney and Albert Bridge was causing concern among residents. Cabinet member for transport Councillor Nick Austin said at the time that there was “no quick-fix solution” and that the council was “pressing TfL to improve junctions and traffic light signals”.