Delays in deciding how Parliament will be restored could add more than £479m to the programme if debates are not held until early or mid-2027, parliamentary officials have warned.
The figures were set out by the parliamentary clerks in an interim response to a Public Accounts Committee report on the Restoration and Renewal (R&R) Programme. The programme had assumed that debates on the options would take place by March 2026, but none had been scheduled by early November.
If debates take place by December 2026, the additional cost is estimated at between £223m and £288m. A decision delayed until early or mid-2027 would result in additional costs of more than £479m, according to the clerks. The estimates include ongoing maintenance and inflationary impacts.
Temporary accommodation delays
Officials also disclosed further delays to the Commons Building and Infrastructure Portfolio, which is intended to provide temporary accommodation for MPs while restoration work is carried out.
The forecast cost of the portfolio has increased from £2.2bn to £2.4bn, including inflation, while its expected completion date has moved from 2039 to 2042.
The R&R delivery authority estimates that the resulting accommodation shortfall on the Northern Estate could extend delivery of the full decant option by “approximately five to seven years”, potentially taking completion to as late as 2050.
Without mitigation, the clerks estimate that the delays could add between £350m and £800m to the full decant option, excluding inflation. That compares with an earlier estimate of £280m to £600m. The officials described the latest figures as provisional.
Potential measures include increasing accommodation within the parliamentary secure line, extending the secure line to nearby government buildings, or procuring facilities outside it.
Options and potential savings
Two principal approaches remain under consideration. A full decant, in which both Houses would move out for most of the works, was previously estimated to cost up to £15.6bn over 19 to 24 years. A phased approach was estimated at up to £39.2bn over 38 to 61 years.
The clerks identified possible savings of between £576m and £1.5bn, excluding inflation, through delivery efficiencies and value engineering. However, they warned that achieving them “could require significant changes to requirements and standards for which the parliamentary appetite for change and any consequential impact on timelines has not been tested”.
The savings are due to be presented to the R&R programme board in March 2027.
The estimated cost of fitting out the Queen Elizabeth II Conference Centre as temporary accommodation for the House of Lords has also increased from £417m to £450m, excluding inflation and VAT. The Public Accounts Committee described the original estimate as “very high”.
Parliamentary authorities said the increase was largely the result of a £10m rise in net construction costs and the transfer of £20m in design costs previously funded centrally. They added that the increase would be absorbed within the £3bn budget for phase one works.
Scrutiny before 2030 decision
PAC chair Sir Geoffrey Clifton-Brown said the programme’s options involved “extremely high figures with very big ranges”.
“At a time of national fiscal constraint, we would expect the parliamentary authorities to examine these figures extremely carefully to see how they can be reduced before the vote on Phase 2 in 2030,” he said.
He added: “The National Audit Office and the public accounts committee will be scrutinising these costs against progress on an annual basis, [which] would be greatly assisted by the existence of an R&R select committee as we recommend.”
A full response from the clerks to the PAC report is expected in due course. MPs are due to make a final decision on the project in 2030, following an initial vote on which options should be developed further.