Environment

North Sea gas platforms eyed for offshore CO₂ storage reuse

Enersea and Carbon Haven are developing a lightweight injection system to repurpose depleted gas platforms for permanent carbon storage.

UK-based Enersea and Dutch company Carbon Haven are working on an offshore carbon dioxide injection concept that could give depleted North Sea gas platforms a second life as permanent storage facilities.

The proposal combines a lightweight injection module with structural and fatigue assessments of existing platforms. Enersea said the work is intended to establish whether ageing structures can support the additional equipment and loads, while determining their remaining service life for carbon storage operations.

Ship-based CO₂ transport

Carbon Haven’s model would allow captured CO₂ from emitters that are difficult to connect to onshore pipeline networks to be transported by ship. At offshore facilities, the gas would be transferred to injection systems before being pumped into depleted reservoirs.

The companies present the approach as a modular alternative that could complement larger pipeline-based carbon capture and storage hubs. Reusing existing assets could reduce capital costs and lead times compared with building new fixed offshore installations, although the concept remains subject to technical, regulatory and commercial assessment.

Potential storage reservoirs would need to be assessed for capacity, containment and monitoring requirements. Injected CO₂ would also require surveillance during operations and after injection had ended.

Engineering and policy challenges

Repurposing hydrocarbon infrastructure for long-term CO₂ injection raises issues including structural integrity under different loading conditions, corrosion and materials compatibility, well integrity, and the safety of ship-to-platform transfer operations. Lifetime-extension studies could identify risks, but remedial work or replacement of platform topsides, jackets or wells may still be necessary.

Long-term liability and monitoring requirements will also influence project development. The UK and EU allow responsibility for stored CO₂ to transfer to the state when specified conditions are met, but the relevant criteria and obligations differ between jurisdictions.

The proposal comes as the UK’s carbon capture, usage and storage sector faces a shift in government funding priorities. Chancellor John Healey has announced a £200m reduction in capital grant funding for CCUS as part of a wider £700m reprioritisation towards the Defence Investment Plan, while £9.4bn of core support for the HyNet and East Coast clusters remains protected, according to the source material.

Development grant funding for the Viking cluster in Humberside has also been maintained, while the Acorn cluster in Scotland has not received a direct grant commitment. Industry concerns have focused on investor certainty and possible delays before the next Spending Review, expected in early 2027.