Nettleham Roundabout scheme submitted for planning with £9.5m forecast cost

Lincolnshire County Council has submitted plans to expand the A46 junction and add a pedestrian and cycle bridge, with construction provisionally scheduled for 2027-28.

Lincolnshire County Council has submitted a planning application for an upgrade of Nettleham Roundabout, with the scheme’s most likely cost estimated at around £9.5m.

The projected cost range is between £7.4m and £12.1m. The council said the final figure would become clearer once a contractor has been appointed.

Junction and bridge improvements

The proposals include an additional lane on the roundabout, new entry and exit lanes, and a combined pedestrian and cycle bridge over the A15 east leg of the junction. New drainage and street lighting are also planned.

The bridge is intended to improve links between communities north of Lincoln and the city, including for users of National Cycle Route 1.

A planning decision is expected in early 2027. Construction is provisionally scheduled to start in spring 2027 and finish in spring 2028, subject to planning approval, land acquisition and procurement.

Funding and future demand

Part of the funding is expected to come from the £20m of capital funding allocated to Lincolnshire County Council through the Greater Lincolnshire Combined County Authority devolution deal in 2024.

The council’s project information puts the scheme’s estimated cost at approximately £10m and says it would fund any amount above the devolution allocation. Its latest announcement said the remaining funding would come from the council’s central government highways allocations.

The council said the upgrade would help the network respond to future demand, including traffic growth associated with the North Hykeham Relief Road. The five-mile relief road is being delivered by Balfour Beatty with £110m from the Department for Transport’s Large Local Majors programme and is projected to be complete in summer 2029.

Land acquisition and contractor procurement are planned for late 2026 or early 2027. No contractor has yet been named.

Cllr David East, executive member for highways at Lincolnshire County Council, said: “Nettleham Roundabout is one of the busiest junctions in Lincolnshire, and congestion can have a significant impact on people’s day-to-day journeys, particularly at peak times. These proposals are about making travel more reliable, reducing delays and helping to ease pressure on nearby local roads.”