HS2 is moving into the next major phase of civil engineering work on the Curzon approaches, the final stretch of the high-speed railway before it reaches Birmingham city centre.
Engineers are due to begin installing concrete slabs on the five interconnected viaducts this week. The slabs will form the decks of the structures ahead of track installation.
Gantry crane to move between viaducts
A 125-tonne gantry crane has been lifted into position above the Lawley Middleway viaduct. It will install the slabs one at a time, moving over an 18-month period from Lawley Middleway to the Curzon 2, Curzon 1 and Duddeston Junction viaducts.
Greg Sugden, HS2 Ltd’s head of delivery for the Curzon approaches, said: “This is a huge moment for the Curzon approaches team, as we begin what is essentially the last major phase of civil engineering works on this section of the route.
“It’s a test of skill and precision, as we must ensure that when the gantry crane arrives at each structure, we’re ready for the deck installation works to begin.
“It will take around 18 months to lay the decks, then HS2’s new elevated gateway into Birmingham will be structurally complete.”
Slabs manufactured in Warwickshire
The reinforced slabs are being produced at Balfour Beatty VINCI’s purpose-built factory in Kingsbury, Warwickshire. The 140-strong team at the facility spent four years manufacturing 2,742 segments for the Delta Junction viaducts before switching production to the precision-designed approach slabs.
Malik Kayatas, section manager at Balfour Beatty VINCI, said: “A 125-tonne gantry crane will begin installing deck slabs along a series of interconnected viaducts in Birmingham this week. Sitting on top of the structures, it will move outwards from the city centre on an 18-month journey, marking the next exciting phase of this project.”
Night-time road closures planned
Temporary night-time closures will be introduced on the Lawley Middleway (A4540) between Garrison Circus and Curzon Circus while slabs are installed over the road and public walkways.
A northbound-only closure is scheduled from 10pm to 6am each night between 21 November and 6 December. A full closure in both directions will run from 10pm to 6am each night from 25 November to 2 December, followed by a southbound-only closure from 10pm to 6am from 3 to 6 December.
HS2 said significant progress had been made on all five viaducts, which define the railway’s route towards the planned Curzon Street terminus.