Construction of HS2’s Coventry Road overbridge near Bickenhill has reached its halfway point, 11 months after work began.
The bridge will carry the A45 between Stonebridge Island and Junction 6 of the M42 over the railway, allowing HS2’s four tracks to pass beneath the road on the approach to Interchange Station.
Bridge built in two halves
HS2 construction partner Balfour Beatty Vinci (BBV) is delivering the structure in two halves to keep traffic moving along the existing A45 and limit disruption to the local road network.
Using a top-down construction method, engineers excavated about 7,500t of earth beneath the existing carriageway. They installed 46 piles, reaching depths of up to 23m, and constructed pile caps to support the 2,000t bridge deck.
Thirteen prestressed precast concrete beams were lowered into position during the summer to support the bridge’s 37m span. A further 13 parapet units have been installed on the completed half.
Waterproofing and highway works are expected to finish in the coming weeks, enabling the eastbound section of the bridge to open. A series of overnight and weekend closures will begin on 7 December to allow traffic to switch to the new alignment.
Once the switch is complete, motorists will use a temporary carriageway alignment over the new eastbound section. HS2 Ltd head of delivery Paul Marshall said access to businesses and properties would be maintained during the closures and encouraged motorists to check diversion routes.
Second half due to start in 2027
Work on the second half of the bridge is due to begin in the new year, following a similar construction sequence. Excavation will continue beneath the structure for the railway trace serving HS2’s Interchange Station, about 1.6km away.
The tracks will serve the station’s four platforms, including two 425m-long platform islands.
BBV project manager Richard Husbands described the overbridge as a key crossing on this section of the route and said reaching the halfway stage was an important project milestone.
Above-ground construction is expected to continue throughout 2027, with the bridge structurally complete by the end of that year. Permanent highway works, delivered in liaison with National Highways, will then include lighting, kerbs, drainage and the final carriageway.
The completed bridge and final road alignment are expected to enter use by summer 2028.