Galafoot Bridge works extended to January 2027 after concrete damage revealed

BEAR Scotland says the A6091 crossing will remain open to westbound traffic only until late January after repairs exceeded initial estimates.

Works on Galafoot Bridge in the Scottish Borders are expected to continue until late January 2027 after the concrete deck was found to require more than three times the repairs originally planned.

BEAR Scotland, which is managing the project for Transport Scotland, said the A6091 crossing would remain open to westbound traffic only until the end of January. Eastbound traffic has been diverted since 5 October via the A7 and B6360, adding around 3.9 miles to journeys. Eastbound HGVs are being routed through Selkirk, the A699 and the A68.

Overnight closures revised

The bridge will close in both directions between 19:30 and 06:00 on 2, 12–18 and 24 November. Previously planned overnight closures on 8, 9 and 29 November have been cancelled, BEAR Scotland said on 28 October.

During the overnight closures, westbound traffic will be diverted via the A6091 eastbound, the A68, the A699 and the A7 to Kingsknowe Roundabout. Emergency services will retain access across the bridge at all times.

Additional deck repairs

The extent of the work became clear after the existing surfacing and waterproofing were removed from the eastbound carriageway. The concrete deck slab beneath was in significantly worse condition than estimated.

David Bishop, BEAR Scotland’s South East Bridges Manager, said: “There was always some uncertainty over what we would find once we removed the existing road surface, however there is more than three times as much concrete requiring repairs as originally anticipated.”

He said additional resources had been considered to accelerate the programme, but the condition of the concrete beneath the westbound carriageway and the impact of winter weather remained uncertain.

“Assuming the deck under the other half of the bridge is in similar condition, and we experience weather that would typically be expected during November and December, it is likely that works will need to continue until the end of January 2027,” Bishop said.

VolkerLaser is carrying out the resurfacing and re-waterproofing of the deck, while Geo-Structural is working on the underside of the bridge. BEAR Scotland warned in July that the existing waterproofing had failed, contributing to premature deterioration of the road surface, and that the programme would depend on weather conditions and the extent of concrete repairs required.