Banwell Bypass faces six-month delay and £9.5m funding request

North Somerset Council is being asked to approve extra funding after water-main diversions pushed the scheme’s expected completion into next winter.

The Banwell Bypass in Somerset is facing a six-month delay and a further £9.5m increase in its budget because of challenges relocating water mains.

North Somerset Council now expects the scheme to be completed next winter, rather than next summer. Councillors will consider the additional funding at a meeting on 10 November, which would take the project’s total budget to £114.7m.

Utility works holding up construction

Bristol Water is managing the diversions, which are needed to move underground services out of the bypass construction area while maintaining supplies to local properties and ensuring future access to the network.

The council said the diversions must be completed before parts of the bypass can proceed because the project includes ground improvements such as piling.

Galliford Try, which was appointed to deliver the project in 2024, said the ultimate completion date would be later than expected because of the utility diversion challenges.

“Galliford Try can confirm that the ultimate completion of the Banwell bypass will be later than expected due to utility diversion challenges,” the contractor said.

“North Somerset Council endeavours to arrange all utility diversions required to suit the project construction programme, assisted by our project team who are working hard with all the stakeholders involved to achieve the necessary final diversions and complete the project as soon as possible.”

Costs rise from original estimate

The proposed increase would take the scheme’s cost to £50m above its original £66m estimate in 2019. Costs had already risen to almost £90m following inflation, with further risks identified during detailed design work and site preparation by Galliford Try.

The council’s latest papers state that borrowing is proposed to cover the extra expenditure while it challenges costs and investigates potential recovery. They warn that any spending not funded from another source will remain the council’s responsibility.

North Somerset Council leader Mike Bell said the contractor was continuing to make “good progress on site” despite the delay.

The bypass is intended to relieve congestion in Banwell and improve links between Weston-super-Mare and the A38. The wider scheme also includes walking, cycling and horse-riding routes linking to the Strawberry Line, as well as new woodland, wetland and grassland.