The opening of the Banwell Bypass in North Somerset has been delayed by around six months after additional water main diversion works were identified ahead of the main construction programme.
North Somerset Council now expects the £105m-plus scheme to open later in 2027, beyond its original summer completion target. The project requires significant ground improvement, including piling, meaning the utility diversions must be completed before the main works can progress.
Costs rise after contractor withdrawal
The bypass was approved in 2023 with an initial £56m funding commitment from Homes England. Its estimated cost has since risen following the withdrawal of the original contractor.
The latest delay has renewed concerns about congestion and disruption in Banwell, where traffic continues to pass through the village. Steve Voller, chairman of Banwell Parish Council, said the delay would extend the stress experienced by residents and people travelling through the area, particularly at peak times.
Voller also pointed to the potential effect on emergency services, recalling an occasion when an ambulance had to turn around after traffic in the village came to a standstill.
North Somerset Council leader Mike Bell said work was continuing on site and that the scheme was moving closer to completion.
Nearly a century of proposals
The bypass was first proposed in 1927 to address persistent congestion through Banwell. Local historian Roy Rice has previously said that his uncle, Wally Richards, helped survey the original route and place marker pegs when he was 11.
Once completed, the scheme is expected to reduce traffic through Banwell by up to 78 per cent, according to studies cited by the project. It is also planned to include new walking, cycling and horse-riding routes, links to the Strawberry Line active travel network, and new woodland, wetland and grassland habitats.