A66 upgrade main works set to start in November under nine-year plan

The government has approved the start of major construction on the Northern Trans-Pennine route, but has not published a revised opening date or total cost.

Major construction on the A66 Northern Trans-Pennine upgrade is due to begin in November under a revised nine-year delivery programme, the government has confirmed.

The scheme will create a continuous 50-mile dual carriageway between the M6 at Penrith and the A1(M) at Scotch Corner by upgrading the remaining single-carriageway sections and improving junctions.

Programme details remain limited

The Department for Transport said in July that the project was being delivered in line with the funding position established after the 2025 Spending Review and the subsequent Road Investment Strategy.

The latest Budget announcement provides clarity on the start of the main works, but does not set out a revised opening date. It also does not explain how the nine-year programme compares with earlier schedules or confirm any change to the scheme’s overall cost.

The government said the completed route would improve connectivity between Cumbria and the North East. The project is part of wider investment in northern transport infrastructure, including Northern Powerhouse Rail and the TransPennine Route Upgrade.

Contractor and package activity

Recent procurement notices issued by Kier identify Balfour Beatty, Kier and Aureos, the former highways business of Keltbray, as the three tier-one contractors collaborating on delivery.

Kier has been seeking subcontractors for several work packages, including a £6.5m pavement construction package covering the first two sections of the scheme. The package includes road bases, binder and surface courses, surfacing treatments and planing works, with an advertised delivery period from June 2027 to October 2030.

Another recent opportunity covers the installation of precast concrete beams at the Carleton Underpass. A tender published in October put the estimated value of that package at £10m.

National Highways has already undertaken preparatory work along the route, including vegetation clearance, drainage improvements and strengthening of the central reservation.