A66 dualling cost could reach £2.67bn as delivery extends to nine years

National Highways has disclosed a potential £2.67bn cost for the A66 Northern Trans-Pennine project, while stressing that its funding and delivery plans remain undecided.

The cost of dualling the A66 between North Yorkshire and Cumbria could rise to £2.67bn, National Highways has disclosed at the Highways UK conference.

The potential figure is more than twice the scheme’s original estimated cost and comes as the timetable for the project is extended from five years to nine.

Construction due to start in November 2026

Government Autumn Budget documents confirmed that main construction work is scheduled to begin in November 2026. The project is intended to create a continuous 50-mile dual carriageway between the M6 and A1(M), upgrading the remaining single-carriageway sections between Scotch Corner and Penrith.

National Highways said no final decisions had been made on the programme or its funding.

“We will set out our full programme through our Strategic Business Plan and Delivery Plan in due course, which will reflect the outcome of the Government’s consultation on changes to RIS3. No final decisions have yet been made,” a spokesperson said.

Criticism over delay

The revised programme has prompted criticism from Richmond and Northallerton MP Rishi Sunak, who described the delays as “frustrating”.

The project is intended to improve connections between the North-East and North-West of England. The possible increase in cost and longer construction period add to the uncertainty surrounding one of the region’s largest road schemes, which has faced repeated delays.