TBM completes 3.4km tunnel for Wales power-line scheme

National Grid’s £286.6m Eryri project has driven beneath the Dwyryd Estuary to remove 10 pylons from the national park’s landscape.

A tunnel boring machine has completed a 3.4km drive beneath the Dwyryd Estuary in north-west Wales, marking a major milestone in National Grid’s plan to replace overhead power lines in Eryri National Park.

TBM Buddug broke through on 13 October, travelling from Minffordd to Llandecwyn. The machine’s arrival was ahead of its planned 1 December breakthrough date.

The tunnel will house new 400kV electricity cables, allowing National Grid to remove 3.4km of overhead line and 10 pylons from the protected landscape. The wider Eryri Visual Impact Provision (VIP) scheme is scheduled for completion by 2030.

A complex route beneath the estuary

The tunnel descends from 14m below ground at Minffordd to 57m at the reception shaft in Llandecwyn. Its alignment curves to avoid structures in Penrhyndeudraeth and near Portmeirion, while passing beneath the Network Rail Cambrian Line at three locations and the Ffestiniog heritage railway.

Ground conditions varied significantly along the route, from soft tidal and glacial deposits to faulted mudstone and quartz. The alignment also crossed a 50m-deep buried glacial-fluvial channel beneath the centre of the estuary.

Buddug is a 166m-long, 436t slurry pressure balance machine with a 5.25m-diameter cutterhead. It was refurbished by Herrenknecht in Germany after previously being used on a drainage project in Singapore. The drive required 2,769 precast concrete lining rings, each 250mm thick.

National Grid senior project manager Stephen Ellison said the lining design had to accommodate both the repurposed machine and the pressures generated by the estuarine geology. Steel-fibre rings were used along most of the route, with steel-reinforced rings specified for the launch and deep scour zones.

Managing unpredictable geology

Hochtief tunnel operations manager Ferenc Lavicska said geology was responsible for most of the project’s challenges. The estuarine setting limited the amount of ground investigation that could be carried out, particularly in the most critical section beneath the water.

The machine was equipped with Herrenknecht’s Borehole Electrical Ahead Monitoring system to help identify conditions ahead of the cutterhead. Its cutting tools were changed to monoblock discs, while additional steel grizzly bars were installed to prevent large boulders from blocking the slurry system.

The team encountered boulders, fault rock and sandy material that placed additional loads on the TBM’s tail skin. On one occasion, material blocked several slurry discharge and suction lines, requiring the system to be isolated and cleared manually.

Maintenance interventions were particularly demanding in areas where water pressure exceeded 3.5 bar. Specialised contractors provided life-support equipment, medical locks, mixed-gas systems and emergency rescue arrangements for work in pressurised conditions. National Grid said preparations also included seeking Health and Safety Executive exemptions for hyperbaric interventions.

Launch design changed

The original design called for the TBM to be lowered through a 15m-wide, 30m-deep circular shaft. This was replaced by an 8m-wide, 14m-deep and 69m-long open launch box at Minffordd.

Ellison said the change provided safer and larger lifting areas for moving equipment and kept personnel further away from suspended loads. The project team also applied experience from National Grid’s Feeder 9 River Humber Gas Pipeline Replacement Project, including the use of round rather than oval grout ports to reduce blockages.

Electric plant was used during tunnelling to avoid exhaust emissions in the tunnel, according to Hochtief. The delivery team included Hochtief UK, Herrenknecht, NKT Cables, Network Rail, Aecom, Hochtief Engineering, Atmos Consulting and Gwynedd Archaeological Trust.

Work continues at both ends

Following the breakthrough, teams are removing TBM components from the reception shaft and preparing to line it with precast segments and waterproofing. Headhouses will then be built over the two shaft structures: a stone barn-style building at Minffordd and a Corten steel structure at Llandecwyn.

National Grid said environmental controls would continue during the remaining works, including monitoring of noise, dust and light, alongside measures to protect local wildlife. The company is also implementing a local workforce and supply-chain strategy.

The new cables must be installed and commissioned before the existing overhead line can be removed and the pylons dismantled.