Highways

Hertfordshire to repair 34 ageing concrete roads

A dedicated programme backed by more than £700,000 will target defects on post-war roads across the county, with most work due before Christmas.

Hertfordshire County Council is carrying out a dedicated maintenance programme on 34 ageing concrete roads, with most of the work scheduled for completion before Christmas.

More than £700,000 was secured earlier this year for repairs to long-standing defects on concrete roads across the county. Many were built on housing estates during the post-war decades and now require specialist maintenance.

Work already completed

Repairs have been completed at Hunting Gate and Spring Lane in Hemel Hempstead, the Gossamers and several other roads in Watford, and Downedge in St Albans. Further schemes are planned across Hertfordshire over the coming months.

Concrete roads expand and contract as temperatures change, which can lead to cracking and movement below the surface. Many were subsequently covered with thin asphalt layers, which can deteriorate as the concrete beneath shifts.

The resulting defects can be highly visible but may not meet the threshold for urgent pothole repairs. The council’s dedicated programme is intended to address those locations through a different maintenance approach and prioritise areas where works will have the greatest effect.

Cllr Stephen Giles-Medhurst OBE, Hertfordshire County Council’s executive member for highways, said: “Many of Hertfordshire’s concrete roads were built more than 50 years ago and continue to play an important role in our local road network. For too long, residents have been frustrated by roads that were visibly deteriorating but often did not meet the criteria for urgent intervention.

“That is why I made the case for a dedicated £700,000 investment to address concrete road defects across Hertfordshire. By taking action now, we can improve residents’ day-to-day journeys, prevent further deterioration and make better use of taxpayers’ money.”

He added that the council was taking an estate-wide approach wherever possible, rather than carrying out isolated repairs, and said continuation and expansion of the programme would be prioritised subject to future budget approvals.