Transport for Wales (TfW) is preparing a major rail replacement operation as Network Rail carries out a £25M programme of upgrades on the North Wales Coast line.
The engineering work will take place during January and February 2027, with planned improvements at Conwy Tubular Railway Bridge, Bodorgan Tunnel, Penmaenbach, Holyhead and Llandudno. The programme also includes platform improvements at Llandudno Junction and new active-travel footbridges at Prestatyn and Pensarn.
TfW said some of the infrastructure has not received significant investment since the 1970s.
Planned closures
The line between Chester and Holyhead will close for three weeks from Saturday 9 January to Friday 29 January 2027. During this period, no trains will run between Chester and Holyhead, or on the Conwy Valley line between Llandudno and Blaenau Ffestiniog.
Services are scheduled to resume between Chester and Llandudno Junction on 30 January. However, the section between Llandudno Junction and Holyhead will remain closed until Friday 5 February, creating a further week-long closure.
Separate engineering work at Chester station will mean no trains between Wrexham and Chester on three weekends in January. Services between Manchester and Cardiff are expected to operate as normal.
TfW said the work had been scheduled for winter to reduce disruption to tourism and local businesses.
Rail resilience investment
TfW planning and performance director Colin Lea said: “Following the introduction of our brand-new trains and more frequent services along the North Wales Coast, this investment is another important step towards providing a more reliable and resilient railway.
“Bringing rail replacement management in-house has allowed us to better coordinate our bus and rail operations.
“We know some journeys will take a bit longer during the closure, so we’re asking customers to check before they travel, plan ahead and allow extra time for their journey.”
Network Rail passenger strategy director Emma Osborn said: “The North Wales Coast is a vital railway connecting communities across the region, and this £25M programme will see our teams deliver several years’ worth of essential upgrades in just four weeks.
“The closure gives us the access we need to carry out this work safely and efficiently, renewing key parts of the railway to make it more reliable and resilient for years to come.”