Highways

A511 corridor cost rises to £84.6m, leaving £13m funding gap

Leicestershire County Council’s cabinet is due to decide in December whether to proceed with the scheme between Ashby and the A50.

Leicestershire County Council is facing a £13m funding shortfall on the A511 Growth Corridor, with the latest estimated cost reaching £84.6m against £71.6m currently available.

The council’s cabinet will decide in December whether to proceed with, modify, pause or cancel the scheme. Officers updated the cost estimate in July, citing significant water and drainage issues along the corridor and complex engineering challenges around the proposed Bardon Link Road.

Funding and scope

The project covers junctions and sections of the A511 between junction 13 of the A42 near Ashby and the A50 Field Head roundabout. The available funding comprises Department for Transport support and developer contributions, according to evidence submitted by the council.

The scheme was valued at £47.57m in its 2021 outline business case. A December 2023 cost plan put the figure at £63.5m, including a £41.712m Department for Transport grant and £21.8m in developer contributions.

Leicestershire County Council appointed Taylor Woodrow for early contractor involvement in September 2025. At that stage, the project was reported as a £65m scheme, with a provisional £41.7m Department for Transport allocation subject to approval of the full business case.

Cabinet decision

The funding position was discussed by the council’s Growth, Highways and Transport Overview and Scrutiny Committee on 5 November. Susan Baum, the authority’s strategic financial manager, described the decision as a “really difficult dilemma”.

She told the committee: “As an authority, we have a revenue funding gap of £85m. We’ve got a capital funding gap of £75m.” Baum added: “We will need to borrow if we can’t fund this… From the business side of things, this is money that we would not otherwise have access to. It is externally funded.”

Councillor Craig Smith, who represents Coalville North, said scrapping the scheme “could not be considered”, citing severe traffic management problems in Coalville. Councillor Andrew Hamilton-Gray, described as the council’s highways lead, said: “From a personal perspective, you have my support but as I said, it is ultimately not up to me”.

Councillor Graham Cooke questioned the scale of the investment, describing it as a “hell of a lot of money thrown into a road” and expressing concern about areas growing and expanding.

Council officers said the scheme would provide “high value for money” if it proceeds. A council spokesperson said: “Work is currently underway to confirm the latest costs and funding position and Cabinet will consider proceeding to construction with the full range of evidence, including the wider benefits for Leicestershire, before making the final decision.”

Programme under review

The council’s project information previously indicated that construction would begin in winter 2026 and finish in winter 2028, with a second-stage contractor expected in late autumn 2026. Two of the Department for Transport’s three business case stages had been approved, while the full business case remained outstanding.

The council says it has partnered with Midlands Highway Alliance Plus to deliver the project through its frameworks. The December cabinet decision will determine whether the scheme moves towards construction on the previously indicated timetable.