Merseyrail Northern Line reopens after £3.5m tunnel works

The Northern Line has reopened following a 27-day closure for tunnel strengthening, waterproofing and power-control upgrades beneath Liverpool city centre.

Merseyrail’s Northern Line has fully reopened after Network Rail completed a £3.5m programme to strengthen and waterproof four Victorian tunnels beneath Liverpool city centre.

The railway between Brunswick and Liverpool Central was closed for 27 days, with trains resuming between Hunts Cross and Liverpool city centre on Saturday 7 November. Work began on Sunday 11 October and was completed ahead of the reopening.

Tunnel waterproofing and strengthening

More than 50 workers removed 92m² of old concrete before applying new concrete. Engineers drilled 6,500 holes into the tunnel walls to inject waterproofing materials, while a further 115 weep holes were installed to direct water into drainage systems.

In total, 1,688m² of tunnel wall was waterproofed. The measures are intended to prevent water entering the tunnels and interfering with the third-rail system that powers Merseyrail’s electric trains.

Network Rail Liverpool area director Paul Owen said: “Waterproofing and strengthening the tunnels means we can keep passengers moving smoothly by protecting the third-rail system which powers Merseyrail’s electric trains.

“It’s all part of our ongoing investment plan and commitment to run a reliable railway for the future and keep the city region moving.”

Merseyrail chief operating officer Stephen Dodd said the upgrades would “strengthen the long-term reliability of the Northern Line and help reduce the risk of future disruption”.

Power-control improvements

Network Rail also modernised power-control systems across the Northern and Wirral lines during four extended Sunday closures. The improvements are designed to make it easier to isolate and switch off sections of electrified railway, supporting faster and safer maintenance and fault response.