Clifton Hampden bypass opens after 62-hour traffic switch

Vehicles are now using the first completed sections of Oxfordshire’s £37m bypass, linking the B4015 with the A415 at Culham.

Part of the Clifton Hampden bypass in Oxfordshire has opened to traffic after contractor GRAHAM completed a 62-hour operation to switch vehicles onto newly built sections of road.

The switch changed access arrangements for Culham Science Centre, the Culham Site No.1 business area and Culham railway station. During the closure, crews carried out excavation, pavement construction, drainage connections, road marking and signage installation.

Work continues on bypass construction

The change allows existing road sections to be incorporated into the bypass alignment while maintaining local connections. Construction is continuing on earthworks, embankments and drainage, with GRAHAM reporting that all five major culverts are being installed and significant parts of the permanent drainage network are now in place.

The bypass has a budget of approximately £37m and will provide a 2.2km single-carriageway link between the B4015 Oxford Road and the A415 at Culham Science Centre. It is intended to divert through-traffic away from Clifton Hampden village.

The scheme is one of three contracts in Oxfordshire County Council’s £332m Didcot and surrounding areas major infrastructure programme, known as HIF1. The programme is intended to improve connectivity and journeys across the area.

John Deery, project director at GRAHAM, said: “It’s a great feeling to see cars on the new road. A lot of work went into that weekend, and I’m proud of how the team and our supply chain pulled together to get it done.

“We’ve worked alongside Oxfordshire County Council for a long time now, and that relationship really matters on a job like this. We plan together, we’re honest about the challenges and we tackle them together.”

Deery said the bypass and the Didcot to Culham River Crossing were complementary elements of the wider infrastructure programme.