Passenger services on the first section of East West Rail are not expected to begin this year, despite earlier plans for trains to start running in 2026.
East West Rail, the Department for Transport (DfT) and the RMT confirmed the continuing uncertainty during a Transport Committee meeting held the previous day. The delayed service will connect Bicester with Bletchley and Milton Keynes.
Dispute over onboard safety roles
The dispute centres on whether trains should operate with a second safety-critical member of staff. The RMT says customer service staff proposed for the service should have full responsibilities for evacuation, line protection and managing the platform-train interface.
RMT general secretary Eddie Dempsey said: “We’ve maintained a position around maintaining a second, safety critical person on trains.”
He said the union’s involvement related to passenger services and staffing, adding that consultation on staffing arrangements had only begun in July despite discussions having started in 2024.
“It’s not an argument about who presses a button to open the door,” Dempsey said. “It’s about who has got a role in managing the platform train interface process.”
Chiltern Railways managing director Tony Baxter said the line had been designed for driver-only operation, with one person holding full safety accountability, including door operation and dispatch.
“In terms of the safety validation, we have done a lot of work around that,” Baxter said. “We can’t finalise safety validation until we have a method of operation but we are very confident that there’s nothing unique or particular to that line of route, which is different to the rest of our route, that will present any risks.”
Earlier delays resolved
Infrastructure work on East West Rail Connection Stage 1 was completed in late 2024, and the first test train ran on the route in October that year. Passenger services were initially scheduled to start in 2025, but projected dates have repeatedly moved.
RMT general secretary Eddie Dempsey attributed some earlier delays to technical issues involving land ownership near one station and the late award of the operating contract following the 2024 general election.
Baxter said the relevant station and train modifications were now ready. Chiltern Railways was appointed operator in March 2025, with preparations including rolling stock modifications, driver training and recruitment.
DfT programme director for East West Rail Jodie Lofthouse said the risk of a dispute had been monitored before Chiltern Railways was selected. “That was always one of the core risks at the top of the risk register,” she said.
Rosemarie Hopkins, the DfT’s interim director for East West Rail, said the delay had caused reputational damage but was not expected to have a material effect on the cost or timetable of later phases.