Engineers working for Skanska Costain Strabag (SCS) have broken through into the concrete-lined Old Oak Common station box, creating a connection between the future HS2 station and the wider route towards Birmingham.
The breakthrough forms part of a 14km tunnel between Old Oak Common and the West Ruislip portal in north-west London. SCS began work on the tunnels in May 2024 from a crossover box at Victoria Road.
Mined tunnel section completed
About 100,000 tonnes of London clay were excavated during the work. HS2 Ltd said the material has been reused on other UK schemes.
The section was excavated using tunnel excavators rather than tunnel-boring machines because the route narrows from two tracks to one between the crossover and the station. The mined sections are approximately 360m long and were finished with a sprayed-concrete lining followed by a cast-in-situ concrete lining installed using travelling formwork.
The breakthrough into the station box, following completion of the northbound tunnel on 13 October, used a method not previously deployed on HS2. The tunnel dividing wall was cut into blocks and pushed out from the station side into the completed tunnel, in a process likened to removing pieces from a Jenga tower.
SCS operations managing director David Hannon said the breakthrough was “a significant milestone for the project” and credited the teams working underground and on the surface. He added that safety and productivity would remain central to the work.
Progress towards Birmingham and Euston
HS2 Ltd said all deep-bore tunnelling between London and Birmingham is now complete, while more than 80% of major structures are either under construction or finished. The company also reported that construction output exceeded its 2025/26 plan by more than 10%, with six major milestones achieved ahead of schedule.
Two tunnel-boring machines launched from the eastern end of the Old Oak Common station box earlier this year are continuing their 7.2km drives towards the planned Euston terminus. They are expected to arrive in mid-2027.
When operational, HS2 is intended to provide a non-stop journey of about 225km between Old Oak Common and Birmingham Curzon Street in approximately 45 minutes. The railway is expected to more than double peak-time seating capacity between London and Birmingham.
HS2 Ltd chief executive Mark Wild said the breakthrough brought the programme closer to its ambition of delivering the railway between Old Oak Common and Birmingham Curzon Street by 2037, or earlier. He said the reset of the wider programme was focused on safe and efficient delivery at the lowest reasonable cost.
Interchange station development
Old Oak Common is being developed as an interchange linking HS2 with the Elizabeth line, Great Western Railway services and Heathrow Express. The station is being fitted out with six 450m HS2 platforms alongside eight conventional-rail platforms.
Station construction partner Balfour Beatty Vinci Systra oversaw platform construction, with Expanded acting as subcontractor.
Rail minister Peter Hendy said the milestone moved the project closer to delivering a transport hub that would connect London with the high-speed railway and support additional rail capacity, economic growth, homes and jobs in west London and the West Midlands.