The railway between Leeds and York has reopened following nine days of upgrade work at Church Fenton as part of the Transpennine Route Upgrade (TRU).
Between Saturday 24 October and Sunday 1 November, engineers installed the new Common Lane railway bridge and completed the fitting of overhead power lines. Network Rail said the previous bridge, built in 1901, was approaching the end of its lifespan.
The replacement was brought forward by a year while preparations were made for the future installation of overhead line equipment, allowing TRU to maximise its access to the operational railway.
Work completed despite Storm Boelo
Activities were rescheduled ahead of Storm Boelo, allowing the work to be paused temporarily when conditions became unsafe. Replacement bus services operated throughout the closure.
Adam Sellers, TRU senior sponsor, said: “We’ve completed this major work at Church Fenton safely and on time, bringing us a step closer to more frequent, faster, greener trains between York, Huddersfield, Leeds and Manchester.
“A big thank you to our teams who worked around the clock and in very challenging weather conditions to deliver this latest milestone.”
Carl Harland, TRU customer lead for Northern, said the works were “an integral part of transforming the route between Leeds and York” and thanked customers for their patience during the closure.
Utility relocation to continue
Utility services diverted during the bridge installation will now be relocated within the new structure. The road is scheduled to be restored and reopened in June 2027.
Network Rail also carried out improvement work on the East Coast Main Line in North Yorkshire over the past two weekends. The programme included track and points renewals, overhead line equipment and drainage upgrades, vegetation management and platform improvements.
The organisation said the work would improve railway reliability and provide smoother journeys for passengers.