Heidelberg Materials says a resurfacing scheme on the A689 in Cumbria achieved a 21% carbon reduction compared with standard hot-mix asphalt.
The work, carried out for Westmorland and Furness Council, covered 1.5 miles between Harbut Lodge and Alston War Memorial. It used 1,150 tonnes of CarbonLock biogenic asphalt from Heidelberg Materials’ Keepershield plant near Hexham, alongside an electric Ammann eABG 4820 paver.
Biogenic binder and electric paving
Heidelberg Materials says CarbonLock contains biogenic material in the binder, allowing it to absorb and store atmospheric carbon dioxide during the asphalt’s life. The company says the carbon remains locked in when the material is recycled.
The Ammann eABG 4820 can lay up to 1,200 tonnes of asphalt on a single charge, according to Heidelberg Materials. The company describes it as the largest electric-drive paver on the market and says it reduces emissions associated with road laying.
Adrian Stubbs, regional general manager at Heidelberg Materials Contracting, said: “This was the first time we have used CarbonLock biogenic asphalt as part of framework agreement and it was an excellent example of how we can help our clients meet their carbon reduction goals. We worked to a tight schedule and delivered the improvement works on time, ensuring further planned work was not impacted, and provided a 21 per cent carbon reduction compared with laying standard hot-mix asphalt.”
Westmorland and Furness Council has described the project as a carbon exemplar scheme and said it will monitor and evaluate its performance.
Kieron Tetchner, the council’s lead network manager, said: “To meet council priorities, and as part of our drive for service innovation, we jointly challenged the highways team and Heidelberg Materials’ engineers to design a scheme using CarbonLock biogenic asphalt and electric vehicles wherever possible to reduce the overall carbon and environmental footprint of the project.”
Framework agreement
Heidelberg Materials said it secured the council’s highway framework agreement in 2024 following a competitive tender. The contract award notice published on Find a Tender on 8 August 2024 names Hanson Quarry Products Europe Ltd, trading as Hanson Contracting, as the single supplier for core surfacing in Westmorland and Furness.
The agreement covers 2024 to 2027, with the option of three one-year extensions. It is valued at £60m excluding VAT and attracted four tenders. Heidelberg Materials was formerly known as Hanson UK.
The company has not disclosed the dates or cost of the A689 works. The announcement also does not set out how the 21% carbon reduction was calculated.