City Thameslink station will close for more than seven months in 2027 while Network Rail replaces all 10 of its escalators.
The closure is scheduled to begin on Monday 17 May and continue until late December. Thameslink trains will run as normal during the works but will not call at City Thameslink.
Escalators have reached end of life
Network Rail said the escalators had been in service for more than 35 years and had reached the end of their operational life. Recent flooding had accelerated their deterioration, affecting their long-term reliability.
The infrastructure manager said replacing all 10 escalators during one planned station closure was the least disruptive and most efficient option. The programme will also include other improvement works at the station.
Lucy McAuliffe, Sussex Route Director for Network Rail, said: “We know closing City Thameslink is a significant change and we’re sorry for the disruption it will cause. This is not a decision we have taken lightly.”
She added: “City Thameslink’s escalators are at the end of their operational life and, by replacing them now, alongside other improvement works in the station, we’re tackling the root causes of access disruption for passengers in one go.”
Passengers directed to Blackfriars
Passengers will be advised to use nearby London Blackfriars station during the closure, where additional staff will be available to help with alternative journeys.
Thameslink Customer Excellence Director Natasha Grice said the operator would work with customers, local businesses and the wider community before and during the closure, providing travel advice and updates.
Network Rail said the renewed escalators would be designed to support safer, more dependable and accessible journeys when City Thameslink reopens in December 2027.