Major construction on land required for the A5 Western Transport Corridor will not begin until after 31 December 2026, Northern Ireland’s Department for Infrastructure has told more than 300 affected landowners.
The update covers Section 2 and Section 3 Phase 1B, running from south of Strabane to Ballygawley. Until the end of 2026, activity on the land will be limited to surveys and other essential preparatory work.
Compensation process disrupted
The department said legal proceedings and the quashing of vesting orders had disrupted the normal compensation process and delayed access to compensation funding for some landowners.
Claims relating to evidenced financial impacts will be assessed independently by Land & Property Services on a case-by-case basis. The department said it would also meet reasonable professional fees for agents representing landowners.
Since a High Court judgment in June 2025, every affected landowner has been offered an individual meeting with the project team. Department officials have also continued to meet the Ulster Farmers’ Union, including at senior official level.
The department acknowledged “the uncertainty that landowners, their families and businesses affected by the A5 Western Transport Corridor have faced over a prolonged period” and has published a questions and answers page for those affected.
Court order still awaited
The Court of Appeal in Belfast overturned the High Court’s ruling on 6 October 2026. The case covered environmental impact assessment, human rights and compliance with climate change legislation. Lady Chief Justice Dame Siobhan Keegan described the litigation history as “long and tortuous”.
The Department for Infrastructure said it was still waiting for the formal order giving effect to the judgment. It also said a firm construction date would be premature until it was clearer whether any party would seek leave to appeal.
The department expects the land to revert to it once the court issues the formal order. The release did not provide a date for that order or for the start of construction.
Cost estimate under review
The department said the £1.7bn figure reported in the media was not its latest published estimate. Its emerging estimate for the 55km Phase 1B section was about £1.2bn in October 2024, although estimates are now under review.
Spend on the project up to 2025/26 was put at £192.5m.
The full scheme is intended to provide 85km of new road between New Buildings and the border at Aughnacloy, including 82km of dual carriageway. Contractors have been appointed for each of its three sections.
The department said the project had been subject to three public inquiries and four legal challenges.